Goodmans publishes update on potential impact of coronavirus on construction projects

0
956

Ontario Construction News staff writer

With Canada and much of the world under lockdown due to the global COVID-19 pandemic, workplaces are experiencing closures and layoffs, including construction sites of major projects.

Goodmans LLP, a transaction law firm, has published an update on the potential impact of COVID-19 on construction projects in Canada, specifically in the context of force majeure clauses. The virus has already disrupted supply chains and reduced labour forces in Canada and across the globe and has the potential to significantly adversely affect construction projects, the firm says in the update.

“On every construction project, there is potential for an unexpected event outside of the parties’ control. These events are commonly referred to as force majeure events, and typically include natural disasters (or other “acts of God”), fires, flood, war, labour disputes, strikes, and lockouts,” Goodmans says in its update.

“Most construction contracts include a force majeure clause that excludes liability for a party’s failure to perform its contractual obligations in the face of a force majeure event. These clauses are an important tool for risk allocation, and are often tailored to industry-specific and project-specific risks that render performance impossible (or in some contracts, imprudent, substantially more difficult, or substantially more expensive). With a force majeure clause, the parties are generally excused from penalties or damages due to failed or delayed performance.”

Some clauses specifically list diseases, plagues, quarantine restrictions, and/or “epidemics as triggering events, many do not, says Goodmans.

“One example is the Canadian Construction Documents Committee (CCDC) 2 stipulated price contract, which lists items such as labour disputes, strikes, lockouts, fire, abnormally adverse weather conditions, and any cause beyond the contractor’s control other than one resulting from a default or breach of contract. In these cases, COVID-19 may still be captured in a broader category such as ‘emergency’ or ‘any cause beyond the Contractor’s control,’ but that classification may be open to challenge by an adverse party.”

Goodmans offers recommendations:

  • The COVID-19 outbreak will continue to impact all levels of the supply chain, including the availability and prices of materials, manufacturing, logistics, and manpower. Furthermore, as we have seen over the past few weeks, different levels of government have provided guidance and recommendations addressing how to conduct oneself both inside and outside of the workplace
  • This includes limiting the size of crowds and ‘social distancing.’ These recommendations will affect the workplace, including construction sites. A vibrant construction site often includes more than 50 people, and sometimes hundreds. It is possible these scenarios may broaden the scope of what may constitute a force majeure event. If borders are closed to goods or supply-chain disruptions, these too could potentially amount to force majeure events

“Regardless of the outcome of COVID-19 and the time it takes for the situation to abate in Ontario, it is clear that contractors and owners should carefully review their contract documents and force majeure clauses as part of assessing business risk. Requisite notices should be given promptly and in accordance with the contract to ensure contractual rights are protected,” says Goodmans.

Moving forward, stakeholders should:

  • Carefully review their contract documents and force majeure clauses (if any)
  • Contact suppliers to ascertain the status of current and future deliveries, and plan for contingencies
  • Contact members of the workforce (including unions and trades) to determine whether any stoppages or reductions in manpower are anticipated, and plan for contingencies.

“Finally, to a large degree, we are navigating uncharted waters. While the legal issues will play out over the weeks and months ahead, we should not lose sight of the fact we will all be affected by this pandemic. Irrespective of contractual terms, cooperation in the workplace will be required to ensure the health and safety of all of those involved in the construction industry.”