HomeAround the provinceBarrie reopens Mapleview Drive East more than six weeks ahead of schedule

Barrie reopens Mapleview Drive East more than six weeks ahead of schedule

Ontario Construction News staff writer

Mapleview Drive East reopened to through traffic Oct. 8, more than six weeks ahead of schedule, as construction continues on a major road and infrastructure improvement project.

The road was originally scheduled to reopen Nov. 20. The closure was required for work that included replacing a box culvert at Hewitt’s Creek.

Motorists should continue to expect temporary lane closures, lane restrictions and delays while crews complete the remaining work.

The project includes installing concrete centre medians at the Royal Jubilee Drive/Lally Terrace and Chef Lane intersections. Once the medians are in place, both intersections will be restricted to right-in/right-out movements, eliminating left turns to and from Mapleview Drive East.

The broader Mapleview Drive East Transportation Improvements Project extends from Yonge Street to Prince William Way and is intended to accommodate planned growth through 2031.

Mapleview drive barrieWork includes widening the road to four through lanes, intersection improvements, multi-use trails on both sides of the road, new storm and sanitary sewers, stormwater infrastructure and street lighting.

The project also includes traffic signal upgrades at Lily Drive, Kneeshaw Drive and Royal Jubilee Drive, along with improvements at Yonge Street.

Primrose Contracting (Ontario) Inc. was awarded the construction contract. The overall project was originally scheduled to run from January 2026 to spring 2028.

The early reopening applies to through traffic on Mapleview Drive East, not completion of the entire project.

Project updates are available at barrie.ca/roadwork.

Robin MacLennan, Editor, Ontario Construction News
Robin MacLennan, Editor, Ontario Construction News
Robin MacLennan has been a reporter, photographer and editor at newspapers and magazines in Barrie, Toronto and across Canada for more than three decades. She lives in North Bay. After venturing into corporate communications and promoting hospitals and healthcare, she happily returned to journalism full-time in 2020, joining Ontario Construction News as Writer and Editor. Robin can be reached at rmaclennan@ontarioconstructionnews.com
RELATED ARTICLES
- Advertisement -