Construction schedule for the new Civic development

Ontario Construction News staff writer

The Ottawa Hospital has outlined its construction timeline for its new $2.8 billion hospital:

  • 2021: Complete program and space planning done; proposals to qualify and select proponents to design, build, finance, and maintain
  • 2022: Start of on-site parking garage to be completed end of 2023; select the preferred proponents and long-term partners for the new Civic development
  • 2023: Complete the business and financial plan and financially close the project
  • 2024: Construction begins for four years
  • 2027: Transition management to the new site
  • 2028: Grand opening
Mark Buckshon
Mark Buckshon
Mark Buckshon founded the precursor business behind Ontario Construction News in 1989. Earlier, he worked as a journalist and sub-editor, including a stint on the Bulawayo Chronicle in 1979-80, during the transition from Rhodesia to Zimbabwe.  He has lived in Ottawa since 1981. While most publishers achieve their role through a sales/business development career, Mark developed his business skills after succeeding as a journalist, and he continues to enjoy actively writing, editing and contributing to the publication. Mark can be reached at buckshon@ontarioconstructionnews.com