Ontario Construction News staff writer
Bot Construction Ltd. has been awarded two Ontario Ministry of Transportation contracts worth a combined $53 million for bridge and road construction along the future Highway 413 corridor in Brampton and Caledon.
The contracts include construction of bridges to carry Bovaird Drive in Brampton and Hurontario Street (Highway 10) in Caledon over the planned 52-kilometre highway.
Work has begun at both locations, with completion scheduled for November 2028.
At Bovaird Drive, the work includes construction of a new bridge and approach embankments, along with widening and reconstruction of the existing road. The road will be raised between Heritage Road and approximately 500 metres west of Mississauga Road to accommodate a future Highway 413 interchange.
In Caledon, work includes a new bridge carrying Highway 10 over the future highway, approach embankments and pavement resurfacing between Old School Road and King Street.
Temporary traffic detours will be constructed at both sites to accommodate the work.
“We are pleased to receive award of these contracts and to be building part of the new Highway 413,” said Steve Bot, vice-president and general manager of Bot Construction.
The planned highway will connect Halton, Peel and York regions, extending from Highway 400 to the Highway 401/407 ETR interchange. It will also connect with highways 10, 410 and 427.
“The scope of road and bridge works on these two contracts fit perfectly with our company’s expertise,” Bot said.