OC Transpo reaches construction milestones to the east and west

Ontario Construction News staff writer

OC Transpo has reached a new milestone in construction of the O-Train Stage 2 east extension.

More than 12 kilometres of new track has been laid for the extension of Line 1, which runs east from Blair Station into Orléans.

Officials announced the milestone on social media and now construction will focus on installing electrical components including overhead wires, signalling and communications equipment.

The eastern extension of Stage 2 of LRT will bring trains to Trim Road and is expected to be completed in early 2025.

On Nov. 1, the agency announced the completion of excavating on two tunnels along Kichi Zibi Mikan, Byron Linear, and Connaught Parks. The next stage of construction involves pouring the roof and walls of the tunnel, backfilling, and installing track infrastructure.

oc transpo transitway image

“Our crew also poured the largest amount of concrete in a month with a volume of 7503 m3, 1000 m3 more than targeted,” OC Transpo stated.

Robin MacLennan, Editor, Ontario Construction News
Robin MacLennan, Editor, Ontario Construction News
Robin MacLennan has been a reporter, photographer and editor at newspapers and magazines in Barrie, Toronto and across Canada for more than three decades. She lives in North Bay. After venturing into corporate communications and promoting hospitals and healthcare, she happily returned to journalism full-time in 2020, joining Ontario Construction News as Writer and Editor. Robin can be reached at rmaclennan@ontarioconstructionnews.com