As the City of Mississauga prepares to defend a moratorium at the Ontario Land Tribunal, Ontario Premier Doug Ford says the province will work with municipalities on proposed artificial intelligence (AI) data centre developments rather than “ramming something down their throat.”

“If the municipality doesn’t want it, move it to another municipality that does,” Ford told reporters at Queen’s Park on Nov. 18, announcing his plan to meet with newly elected Mississauga Mayor Alvin Tedjo to discuss proposed data centre developments in the city.

Mississauga will defend its one-year moratorium on large data centre construction at the OLT following appeals by two developers. Prologis and Montcrest Asset Management have challenged the city’s interim control bylaw, arguing it lacks a proper planning rationale and exceeds municipal authority.

Mississauga council unanimously approved the bylaw Sept. 16, temporarily prohibiting new major digital infrastructure facilities, including data centres, with peak electricity demands of 10 megawatts or more. The restriction applies across the city and includes conversions and expansions of existing facilities.

During the one-year pause staff will review planning implications of large-scale data centres, including electricity demand, noise, land use and potential impacts on surrounding communities. The bylaw can be extended for a second year.

Prologis is challenging the restrictions affecting its proposed two-storey, 220,000-square-foot data centre on former farmland at 0 Tenth Line West, near Argentia Road in Mississauga’s Meadowvale area. The project has a proposed power demand of 40 megawatts, according to reporting by The Canadian Press.

The company’s development application, submitted in December 2025, remains under review by the city.

In its appeal, Prologis argued the moratorium was the result of ratepayer pressure and political priorities rather than a sound planning rationale. The company also said delays and uncertainty surrounding the bylaw had cost it two potential data centre clients.

Montcrest is challenging the bylaw’s impact on its Tahoe Centre property near Dixon Road and Eglinton Avenue, south of Toronto Pearson International Airport. The company argues the city is using the bylaw to restrict the potential future use of its land while investigating an issue it does not have the authority to regulate.

The developer wants clearer guidelines for future development and is committed to working within provincial regulations for any data centre proposals it advances.

No hearing dates have been established.

At least six Ontario municipalities have introduced temporary restrictions on data centre development in recent months.

The provincial government has also been developing a Data Centre Playbook to establish guidance for future development and approvals. Economic Development Minister Vic Fedeli recently said his office had received about 100 submissions for data centre projects and that the government wanted to move ahead with approvals sooner rather than later, according to Global News.

Ford’s comments could complicate calls for provincewide restrictions. Green Party Leader Mike Schreiner said he has heard concerns from residents in Mississauga, Oakville, Sault Ste. Marie and Hamilton about electricity demand and the ability of communities to control development.

The dispute has implications beyond Mississauga, as municipalities across Ontario consider how to manage the land-use, electricity and infrastructure demands associated with a growing data centre sector.

 