Ontario Construction News staff writer
An American logistics and warehouse developer is appealing the City of Mississauga’s one-year moratorium on data centre development, arguing the temporary ban lacks a sound planning rationale and has delayed a proposed project.
San Francisco-based Prologis filed an appeal with the Ontario Land Tribunal in November, challenging the city’s interim control bylaw, which took effect in September following a unanimous council vote.
The company applied in 2025 to build a two-storey, 220,000-square-foot data centre on former farmland near Tenth Line and Argentia Road in Mississauga.
“After careful consideration of Council’s decision and the options available to us, Prologis has filed an appeal with the Ontario Land Tribunal regarding the City of Mississauga’s Interim Control By-law,” Global News reported.
“Our commitment to Mississauga remains unchanged. We believe a carefully planned data centre in Meadowvale Business Park could bring significant, lasting economic benefits to the community.”
Mississauga council imposed a one-year moratorium on new data centre development on Jul. 29, giving municipal staff a chance to prepare a report on potential impacts of facilities. Residents opposed to data centre development raised questions about the scale of operations, impact of water resources, electricity use and noise.
Prologis submitted a proposal in August 2025, seeking a zoning by-law amendment and site plan approval for a two-storey, 220,000-sq. ft. data centre at Tenth Line West and Argentia Road.
In its submission to the OLT, Prologis accuses the moratorium was driven by “ratepayer pressure and political priorities.”
“After careful consideration of council’s decision and the options available to us, Prologis has filed an appeal with the Ontario Land Tribunal regarding the City of Mississauga’s Interim Control By-law,” the company said in a statement.
“Our commitment to Mississauga remains unchanged. We believe a carefully planned data centre in Meadowvale Business Park could bring significant, lasting economic benefits to the community.”
The city said it is preparing a response and will submit documents to the tribunal.
The appeal could have implications for other Ontario municipalities considering restrictions on data centre development.
Nick Tsergas, founder of the advocacy group Stop The Datacentre, said the tribunal’s decision could influence how municipalities approach temporary development bans.
If the tribunal rules in favour of Prologis, the company could proceed with its proposed development, although the moratorium could remain in effect elsewhere in Mississauga.
Alternatively, the decision could result in the moratorium being overturned entirely, Tsergas said.
He added that municipalities across Ontario and Canada will be watching the outcome.
Prologis also confirmed it submitted recommendations to the provincial government as part of its work to develop guidelines for data centre approvals.
Economic Development Minister Vic Fedeli recently told Focus Ontario that his office had received about 100 submissions related to data centre development. The province is looking to move forward with approvals for new projects, he said.