Substantial completion reached for first set of Eglinton Crosstown West Extension tunnels

Ontario Construction News staff writer

Infrastructure Ontario (IO) and Metrolinx recently announced substantial completion of the first set of tunnels for the Eglinton Crosstown West Extension (ECWE) project. The first advance tunnel contract includes two 6.3-kilometre tunnels stretching from west of Scarlett Road to Renforth Drive.

The contracting team, West End Connectors, completed the tunnels, cross passages, headwalls for future stations, utilities, and emergency exit buildings among other construction elements. The design-build-finance project was delivered through IO’s Public-Private Partnership (P3) model.

West End Connectors includes a construction team consisting of Aecon Infrastructure Management Inc., Dragados Canada Inc., Ghella Canada Ltd. and design team of TYPSA Inc. and EXP Services Inc.

An elevated guideway and second set of tunnels (the second Advance Tunnel contract) are currently under construction, while the stations, rail and systems contract is in procurement. Once work on all the contracts has been completed, the Eglinton Crosstown West Extension will bring Line 5 Eglinton another 9.2-kilometres west from Mount Dennis LRT station in Toronto to Renforth Drive in Mississauga.

The project is the first phase of work for the 9.2 kilometre extension of the Eglinton Crosstown LRT (future TTC Line 5). The extension will run mostly underground, westward from the future Mount Dennis station to Renforth Drive. The Advance Tunnel 2 Project is the second tunnel package, running between Jane Street and the future Mount Dennis Station.

Once complete, the ECWE will connect to different transit services, including the GO Kitchener Line and UP Express train service at Mount Dennis, TTC bus services at transit stops in Toronto, and GO and MiWay bus services via the Mississauga Transitway.

The Eglinton Crosstown West Extension is being delivered in separate procurement contracts:

  1. A first advance tunnel between Renforth Drive and Scarlett Road.
  2. A second advance tunnel between Jane Street and Mount Dennis Station.
  3. Elevated guideway between Scarlett Road and Jane Street.
  4. Stations, Rail and Systems.
Robin MacLennan, Editor, Ontario Construction News
Robin MacLennan, Editor, Ontario Construction News
Robin MacLennan has been a reporter, photographer and editor at newspapers and magazines in Barrie, Toronto and across Canada for more than three decades. She lives in North Bay. After venturing into corporate communications and promoting hospitals and healthcare, she happily returned to journalism full-time in 2020, joining Ontario Construction News as Writer and Editor. Robin can be reached at rmaclennan@ontarioconstructionnews.com