Publication Date: 19th August, 2026
Certificate:
Notice of Annual Release of Holdback
Name of Owner: York Catholic District School Board
Name of Contractor: Civil Electric Inc.
Date of the Contract between the owner and the contractor: 22/01/2026
Description of the premises: YCDSB St. Paul CES Fire Alarm Replacement Project 2026-56-T
Identification of premises for preservation of liens: Upgrade the fire alarm system at St. Paul Catholic School
140 William Roe Blvd, Newmarket, ON L3Y 1B2A
Amount of holdback that the owner intends to pay to the contractor in respect to services or materials supplied by the contractor during the year immediately preceding the anniversary of the Date of the Contract:
15,416.47 CAD
Intended payment date: 17th August, 2026
Add any additional information about the holdback below: Total holdback is 15%, equal to 15,416.47 CAD
5% will be released after a year
Date Certificate Signed: 18th August, 2026